There are no Summit items on the roster for 12/12/09 meeting, as of the Agenda update dated 1/27/09.
Staff review statistics had no Summit properties listed.
Saturday, January 31, 2009
Wednesday, January 21, 2009
UST Advisory Committee OKs Design for wider Finn Street
WSNAC approved the plan to widen Finn Street. Finn will be widened to 36 feet; a 'normal' street is 32 feet in width. There will be a center turn lane added. Finn is being widened in anticipation of the increased traffic along Cretin from UST's new parking ramp (under construction) and proposed student center.
Article from 1/29/2009 Villager, by Jane McClure (click on article to enlarge):
Finn Street is a north-south street located halfway between Cretin and Cleveland. It extends between Summit and Randolph (the campuses of UST and St. Kate's to the South interrupt the street). Here's a Google Map showing Summit Ave. and Finn St. (click on article to enlarge):
Google Streetview showing intersection of Summit Ave. and Finn St. looking South. The image was probably taken c. summer 2008 (click on article to enlarge):
Article from 1/29/2009 Villager, by Jane McClure (click on article to enlarge):
Finn Street is a north-south street located halfway between Cretin and Cleveland. It extends between Summit and Randolph (the campuses of UST and St. Kate's to the South interrupt the street). Here's a Google Map showing Summit Ave. and Finn St. (click on article to enlarge):
Google Streetview showing intersection of Summit Ave. and Finn St. looking South. The image was probably taken c. summer 2008 (click on article to enlarge):
Tuesday, January 13, 2009
340 Summit New Construction: Garage Variance
The home at 340 Summit was built in 1894. It features a limestone facade and was designed by Allen Stem. The home was recently featured in the Minneapolis Luxury Realestate blog.
The owners have applied for permits to construct a 1300 sf garage behind the house, accessible from Summit via the existing driveway. Two variances are being sought: a side setback variance of 4 or 5 feet, and a square footage variance. The maximum permitted size for a garage is 1000 sf; 1300 is being proposed.
The owners have applied for permits to construct a 1300 sf garage behind the house, accessible from Summit via the existing driveway. Two variances are being sought: a side setback variance of 4 or 5 feet, and a square footage variance. The maximum permitted size for a garage is 1000 sf; 1300 is being proposed.
HPC Agenda Jan 22 Meeting
BUSINESS MEETING AGENDA
5:00
I. APPROVAL OF THE AGENDA
II. APPROVAL OF MEETING MINUTES
A. December 18, 2008 Permit Review/Public Hearing
III. PRE-APPLICATION REVIEW
A. 1225 Estabrook Drive, Marjorie McNeely (Como Park) Conservatory, by
Lunning Wende Associates, for a second preliminary review to construct an
addition to the Como Conservatory along with a terrace, gardens and display
benches. (Boulware, 266-9067)
IV. NEW BUSINESS
A. Saint Paul City Hall/Courthouse, Individual Heritage Preservation Site, adopt
resolution regarding the security/screening alterations proposed for Memorial
Hall and the Kellogg Boulevard entrance. (Spong, 266-9079)
V. HISTORIC RESOURCE REVIEW
A. 437 Mount Ida Street, Historic Resource Review to advise City Council. The
property has orders to remove or repair. The Legislative Hearing Officer
continued the item to the January 13 Legislative Hearing with a City Council
hearing date on January 23. RA-SPC-4715 (Boulware, 266-9067)
VI. ANNUAL MEETING
A. Election of officers for 2009 (Nomination committee: Kralicek, Thomas and
Trout-Oertel)
B. Draft annual report and permit statistics
VII. STAFF ANNOUNCEMENTS
A. December Design Review Statistics (see attached)
VIII. ADJOURN
Attendees: Please enter the City Hall through the Fourth Street entrance.
Commission members: Please call 651.266.9078 if unable to attend.
5:00
I. APPROVAL OF THE AGENDA
II. APPROVAL OF MEETING MINUTES
A. December 18, 2008 Permit Review/Public Hearing
III. PRE-APPLICATION REVIEW
A. 1225 Estabrook Drive, Marjorie McNeely (Como Park) Conservatory, by
Lunning Wende Associates, for a second preliminary review to construct an
addition to the Como Conservatory along with a terrace, gardens and display
benches. (Boulware, 266-9067)
IV. NEW BUSINESS
A. Saint Paul City Hall/Courthouse, Individual Heritage Preservation Site, adopt
resolution regarding the security/screening alterations proposed for Memorial
Hall and the Kellogg Boulevard entrance. (Spong, 266-9079)
V. HISTORIC RESOURCE REVIEW
A. 437 Mount Ida Street, Historic Resource Review to advise City Council. The
property has orders to remove or repair. The Legislative Hearing Officer
continued the item to the January 13 Legislative Hearing with a City Council
hearing date on January 23. RA-SPC-4715 (Boulware, 266-9067)
VI. ANNUAL MEETING
A. Election of officers for 2009 (Nomination committee: Kralicek, Thomas and
Trout-Oertel)
B. Draft annual report and permit statistics
VII. STAFF ANNOUNCEMENTS
A. December Design Review Statistics (see attached)
VIII. ADJOURN
Attendees: Please enter the City Hall through the Fourth Street entrance.
Commission members: Please call 651.266.9078 if unable to attend.
Thursday, January 1, 2009
HPC 2009 Calendar
MEETING TIME: 5:00 PM
MEETING LOCATION: Lower Level, Room 40, City Hall/Courthouse, 15 West Kellogg Boulevard
JANUARY
2 Deadline for January permit applications
8 Annual Meeting
22 Permit Review/Public Hearing
FEBRUARY
5 Deadline for February permit applications
12 Business Meeting
26 Permit Review/Public Hearing
MARCH
5 Deadline for March permit applications
12 Business Meeting
26 Permit Review/Public Hearing
APRIL
2 Deadline for April permit applications
9 Business Meeting
23 Permit Review/Public Hearing
MAY
7 Deadline for May permit applications
14 Business Meeting
28 Permit Review/Public Hearing
JUNE
4 Deadline for June permit applications
11 Business Meeting
25 Permit Review/Public Hearing
JULY
2 Deadline for July permit applications
9 Business Meeting
23 Permit Review/Public Hearing
AUGUST
6 Deadline for August permit applications
13 Business Meeting
27 Permit Review/Public Hearing
SEPTEMBER
3 Deadline for September permit applications
10 Business Meeting
24 Permit Review/Public Hearing
OCTOBER
1 Deadline for October permit applications
8 Business Meeting
22 Permit Review/Public Hearing
NOVEMBER
29 Oct. Deadline for November permit applications
5 Business Meeting
19 Permit Review/Public Hearing
DECEMBER
25 Nov. Deadline for December permit applications
3 Business Meeting
17 Permit Review/Public Hearing
Note: Permits for minor and some moderate work are reviewed by HPC staff; permits for major work andsome moderate work are reviewed by the full HPC at Permit Review/Public Hearings.
MEETING LOCATION: Lower Level, Room 40, City Hall/Courthouse, 15 West Kellogg Boulevard
JANUARY
2 Deadline for January permit applications
8 Annual Meeting
22 Permit Review/Public Hearing
FEBRUARY
5 Deadline for February permit applications
12 Business Meeting
26 Permit Review/Public Hearing
MARCH
5 Deadline for March permit applications
12 Business Meeting
26 Permit Review/Public Hearing
APRIL
2 Deadline for April permit applications
9 Business Meeting
23 Permit Review/Public Hearing
MAY
7 Deadline for May permit applications
14 Business Meeting
28 Permit Review/Public Hearing
JUNE
4 Deadline for June permit applications
11 Business Meeting
25 Permit Review/Public Hearing
JULY
2 Deadline for July permit applications
9 Business Meeting
23 Permit Review/Public Hearing
AUGUST
6 Deadline for August permit applications
13 Business Meeting
27 Permit Review/Public Hearing
SEPTEMBER
3 Deadline for September permit applications
10 Business Meeting
24 Permit Review/Public Hearing
OCTOBER
1 Deadline for October permit applications
8 Business Meeting
22 Permit Review/Public Hearing
NOVEMBER
29 Oct. Deadline for November permit applications
5 Business Meeting
19 Permit Review/Public Hearing
DECEMBER
25 Nov. Deadline for December permit applications
3 Business Meeting
17 Permit Review/Public Hearing
Note: Permits for minor and some moderate work are reviewed by HPC staff; permits for major work andsome moderate work are reviewed by the full HPC at Permit Review/Public Hearings.