Copied below are the drafts of two construction management plans, one for the addition to Sitzmann Hall and the other for the Anderson Athletic and Recreation Complex.

These plans will be discussed at the joint meeting of the WSNAC Campus Development and Traffic, Parking, Safety and Student Relations subcommittees at:

6:30 p.m. Tuesday (April 7),
152
Murray-Herrick.

UNIVERSITY OF ST. THOMAS AND MCGOUGH COMPANIES
SITZMANN HALL CONSTRUCTION MANAGEMENT PLAN
FIRST DRAFT

April 6, 2009

Introduction

McGough Companies will begin construction around May 1, 2009, of an addition to Sitzmann Hall on the northeast corner of Summit and Cleveland avenues.

The four-level, 4,700-square-foot addition will provide additional offices, a chapel, a classroom and storage space for the Center for Catholic Studies, which has occupied Sitzmann since 2003. McGough expects a six-month construction period, with plans to occupy the new areas by Nov. 1.

Timetable

Here is a timetable of anticipated activities. The schedule is subject to change, depending on weather conditions and progress made by crews. The university will update its campus construction web site every Friday from May until the project concludes.

• May 1: A construction fence is installed around the construction site.

• May 8-14: The site is excavated over five working days.

• May 15-29: Footings and foundations are poured over 10 working days.

• May 22-June 5: The elevator shaft is installed over 10 working days.

• June 1-July 7: The structure and exterior are constructed.

• July 7-13: The interior is roughed in.

• July 31-Aug. 20: Exterior brick is laid and roofing is installed.

• July 31-Oct. 9: The interior is completed.

• Sept. 1-15: The site is landscaped.

• Oct. 12-30: The building is furnished and equipped.

• Nov. 1: Faculty and staff move in.

Construction crews

Construction crews will work from 7 a.m. to 3:30 p.m. Monday through Friday.

McGough expects 20 employees on the site. They will park in the ramp at Cretin and Grand avenues or in Lot H, where Opus crews working on the athletic and recreation complex will park.

Construction vehicle traffic

Construction vehicles will use Cleveland and drive onto the property at its northwest corner (Cleveland and the alley). The staging area will include the backyard, the parking lane on the east side of Cleveland from a spot 25 feet north of Summit to the alley, and the equivalent of two parking spaces on the east side of Cleveland north of the alley. A chain-link fence will be installed to separate the staging area from the northbound Cleveland driving lane.

During the week of May 4, excavation crews will remove an estimated 60 truckloads (600 cubic yards) of soil, or an average of 12 loads per day. Trucks leaving the site will turn north on Cleveland to Marshall and west on Marshall to Cretin.

Dust and dirt mitigation

McGough will follow Minnesota Pollution Control Agency and industry standards in controlling dust and dirt during demolition, excavation and construction activities.

The construction site will be watered as necessary to keep the dust problems to a minimum, and Cleveland will be swept and cleaned on an as-needed basis.

Street closings or delays

As noted above, part of the parking lane on the east side of Cleveland will be closed.

Part or all of Cleveland between Portland and Summit will be closed for up to two days in July to allow the city to install a new water main and sanitary sewer near the curb cut of the existing three-car parking bay along the east side of Sitzmann.

Construction site noise

Noise is expected to have minimal impact on the neighborhood. Most construction-related noises will be muffled by the sound of motor vehicle traffic on nearby streets.

Communications

St. Thomas will coordinate all construction project communication.

John Hershey will be the primary contact, with Doug Hennes as a secondary contact. Calls should go to them – not to McGough employees. John and Doug will have regular contact with St. Thomas employees coordinating the construction activities and the McGough on-site superintendent, and will address concerns as quickly as possible.

Beginning in early May, St. Thomas will maintain a construction page on its Web site (www.stthomas.edu/constructionprojects. The page will be updated every Friday, with a recap of what occurred that week and a preview of what will occur in the weeks ahead.

++++

UNIVERSITY OF ST. THOMAS AND OPUS NORTHWEST
ANDERSON ATHLETIC AND RECREATION COMPLEX
CONSTRUCTION MANAGEMENT PLAN
FIRST DRAFT

April 6, 2009

Introduction

Opus Northwest will begin construction of the Anderson Athletic and Recreation Center at the University of St. Thomas in St. Paul on May 26, 2009.

The center will be constructed on the site of the existing Schoenecker Arena, Coughlan Field House and Foley Theater, all of which will be demolished in June. The center, which will include a basketball and volleyball arena, field house with 200-meter track, swimming pool, fitness center, weight room, offices and classrooms, will open by Oct. 1, 2010.

Pending Board of Trustees approval, St. Thomas expects to raze a fourth building – the adjacent O’Shaughnessy Hall – in the summer of 2010 to make way for the new Anderson Student Center on the northeast corner of Summit and Cretin avenues. The student center would open in January 2012.

Timetable

Here is a timetable of anticipated activities. The schedule is subject to change, depending on weather conditions and progress made by crews. The university will update its campus construction web site every Friday from June 2009 until the project concludes in October 2010.

• Mid-April-May 29: Demolition preparation occurs in Foley, Schoenecker and Coughlan, including asbestos abatement in Foley.

• May 26: A construction fence is installed around the building and the staging area, which includes a portion of Lot H.

• June 1: Demolition begins on Foley, Schoenecker and Coughlan, and could take three weeks.

• June 22: Excavation begins for utility tunnels, foundations and water-retention pools.

• July: Work begins on below-grade concrete footings and foundations.

• Mid-July/August: Structural precast and structural steel erection begins.

• September-March: The structure and exterior of the new complex are constructed.

• March-September (2010): Interior and specialty work is completed.

• October (2010): Athletic, faculty and staff members move into the new complex.

Construction crews

Construction crews will work from 7 a.m. to 4:30 p.m. on weekdays, although their schedules could be extended to 6 p.m. during the summer to take advantage of the weather. Crews may work an occasional Saturday if necessary to stay on schedule, with shifts beginning at 8:30 a.m.

Opus expects an average of 40-50 employees on the site during the summer 2009, with crew sizes slowly increasing and running as high as 100+ during the winter and spring of 2010. Crew members will park in Lot H.

Construction vehicle traffic

A site plan will be submitted to the City of St. Paul for approval of construction truck routes.

Construction vehicles will use Cretin, usually coming from Interstate 94, and will not travel on residential streets (e.g., Summit Avenue and Mississippi River Boulevard). The entrance to Lot H from Cretin will be the main entrance point to the site. Most, if not all, vehicles will used the fenced-in staging area of Lot H for layovers. Construction traffic will exit onto Cretin.

During the three-week demolition stage, crews will remove an estimated TBD truckloads (TBD cubic yards) of debris and average TBD loads a day. Trucks leaving the site will turn onto Cretin.

During the four-week site excavation stage, crews will remove an estimated 820 truckloads (13,000 cubic yards) of debris and average 40 loads a day. Trucks leaving the site will turn onto Cretin.

Truck arrivals and departures will be staggered as much as possible to reduce the amount of time that they have to idle on the site.

Dust and dirt mitigation

Opus will follow Minnesota Pollution Control Agency and industry standards in controlling dust and dirt during demolition, excavation and construction activities.

The construction site will be watered as necessary to keep the dust problems to a minimum, and Cretin will be swept and cleaned on an as-needed basis – every Friday and on Mondays through Thursdays depending on conditions.

Street closings or delays

All utility connections for the new complex will be to existing university mains and will not require any relocations within city streets. The internal campus drive between the football stadium and the construction site will be closed for the duration of the project.

Construction site noise

With construction occurring near the middle of campus, noise is expected to have minimal impact on the neighborhood. That distance and the sound of motor vehicle traffic on nearby streets will muffle most, if not all, construction-related noise.

Parking

During construction, St. Thomas will lose up to 394 parking spaces – 71 in Lot E, 23 in Lot F and up to 300 in Lot H – because they are within the building construction footprint or will be used as part of the staging area.

Faculty and staff now park in Lots E and F and commuter students now park in Lot H. During construction, they will park primarily in the new 725-car ramp on the southwest corner of Cretin and Grand, and at least 100 spaces will be available in the southern portion of Lot H for students.

Communications

St. Thomas will coordinate all construction project communication.

John Hershey (651-962-6123 and jwhershey@stthomas.edu) will be the primary contact, with Doug Hennes (651-962-6402 and dehennes@stthomas.edu) as a secondary contact. Calls should go to them – not to Opus employees. John and Doug will have regular contact with St. Thomas employees coordinating the construction activities and the Opus on-site superintendent and will address concerns as quickly as possible.

Beginning in late May, St. Thomas will maintain a construction page on its Web site (www.stthomas.edu/constructionprojects. The page will be updated every Friday, with a recap of what occurred that week and a preview of what will occur in the weeks ahead.



Wednesday, April 1, 2009

2009 HPC Awards Call for Nominations

Nominations are due April 20, 2009

2009 SAINT PAUL HERITAGE PRESERVATION AWARDS CALL FOR NOMINATIONS

The Heritage Preservation Commission of the City of Saint Paul and the Saint Paul Chapter of the American Institute of Architects are co-sponsoring the nineteenth annual Saint Paul Heritage Preservation Awards to recognize projects, individuals and organizations that enhance and celebrate Saint Paul's cultural resources. The 2009 awards will be presented at an evening event as part of a month-long celebration during National Preservation Month in May. The date and location of the event are to be announced.

AWARD CATEGORIES AND CRITERIA:

1. Restoration/rehabilitation/adaptive reuse of an historic building; New addition to an historic building; New construction in an historic area or district

  • Projects must be located in Saint Paul.
  • Projects must have been completed between April 1, 2007 and April 1, 2009.
  • Projects will be judged by:
    • the quality of design, workmanship, and materials;
    • the respectfulness of the building's historic and architectural character;
    • the impact of the project on the surrounding neighborhood/community.


2. Organizations and community education projects (for overall, contributions to preservation, rather than for a bricks-and-mortar project)
  • Organizations and community education projects must be located in Saint Paul.
  • Projects will be judged by:
    • the quality of the work;
    • the relevance of the work to current and emerging preservation issues;
    • the impact of their work on a Saint Paul community/neighborhood.


3. Individuals (for an individual, professional or volunteer, who has made an excellent contribution to heritage preservation in Saint Paul)

  • Individuals will be judged by:
    • the quality of their work;
    • their dedication to preserving Saint Paul's heritage;
    • the impact of their work on the Saint Paul community.


4. Cultural heritage (Project, organization, or individual making a significant contribution to the recognition of the city's cultural heritage)

  • Projects will be judged by:
    • the quality of the work;
    • its impact on the Saint Paul community;
    • the extent to which it embodies preservation values .


5. Vote of Confidence Award (Given to a quality preservation-related project having difficulty)

  • Project must be located in Saint Paul.
  • Projects will be judged by:
    • the quality of the project and the organizations involved;
    • the potential of the project to support preservation values and the Saint Paul community.


6. Historic landscapes: (including cultural landscapes, comprised of plantings and the built environment, and designed landscapes such as cemeteries and parks)

  • Projects will be judged by:
    • the quality of design, workmanship and materials; .
    • the degree of reference to a documented historic landscape, where applicable;
    • compatibility with an historic building or district.


7. Stewardship: (recognizes outstanding efforts toward the long term maintenance and preservation of a historic property or site)

Award winners will be selected by a jury of Heritage Preservation Commission and American Institute of Architect members using the above criteria and the nomination information submitted.

NOMINATIONS FOR THE HERITAGE PRESERVATION AWARDS

To nominate a project, group, or individual for an award, send the enclosed nomination form along with required photographs to the address shown on the form.

NOMINATIONS ARE DUE AT THE SAINT PAUL DEPARTMENT OF SAFETY AND INSPECTIONS (DSI), 375 JACKSON STREET, SUITE 220, SAINT PAUL, MN 55101 BY 4:30 P.M. ON MONDAY, APRIL 20,2009. Incomplete forms may preclude the nomination from consideration, at the jurors' discretion.

QUESTIONS?

Please contact Amy Spong or Christine Boulware of DSI, at (651) 266-9078
Or amy.spong@ci.stpaul.mn.us or christine.boulware@ci.stpaul.mn.us
with questions about the Awards or the nomination forms.

Nomination Form
Note: original form is two-sided.



Tuesday, March 31, 2009

Neighbors want UST to add owner -occupied homes to buyback plans

Article in 3/25/2009 Villager, by Jane Mcclure


Neighbors want UST to add owner -occupied homes to buyback plans


The West Summit N.eighborhood Advisory Committee (WSNAC) is expected to vote on a proposal next month that would expand the University of St Thomas' housing buyback program to include owner-occupied homes around UST's St. Paul campus.

St.Thomas agreed to purchase and renovate 30 houses over a 12-year period as part of its 2004 agreement· with the city to expand its campus boundary.The intent was to fix up student rental-properties and sell them to owner-occupants. Ten houses have been bought and resold through the program so far.

Over the past year, university officials and WSNAC . members have received requests to expand the program to include owner-occupied homes that may be slated to become student rental properties, according to Jeanne Matross, co-chair of WSNAC's Housing Sub-committee. Matross' committee has proposed that the purchase of owner-occupied homes be limited to an area bounded by Marshall, Prior, Goodrich and Cretin/Exeter [A]venues. That is less than half the size of the area targeted by the full housing buyback program, which includes parts of the Merriam Park and Macalester-Groveland neighborhoods.

"This is coming from neighbors who are saying, 'Boy, wen really like you to protect our blocks,' " said St. Thomas neighborhood liaison John Hershey.

Over the past year, reSidents on- Laurel Avenue and Powell Street approached St. Thomas about buying two owner-occupied homes that went up for sale on their blocks, rather than see the homes become student rentals. Both of the houses sold on the private market and at least one was purchased by a family for its student-child and friends to live in.

WSNAC members would like a better sense of how many houses could potentially be included in an expanded buyback program. The committee laid over a decision on the policy change on March 10.

Debate over changes to the housing buyback program has been heated in the past. When the program began, St. Thomas bought the rental properties' and made renovations before they were resold to owner-occupants. Now houses are purchased and the new owners are given money to make the improvements themselves.

Two years ago, WSNAC, members and neighborhood residents battled over which blocks should get priority when rental housing is purchased. At the heart of that debate was whether St. Thomas should target home purchases on blocks that are already largely rental or whether it should focus on protecting blocks that are still largely owner-occupied. Some subcommittee members quit in protest when WSNAC opted for the latter.

The push for setting specific bonndaries arose after the university purchased a student
rental home on Stanford Avenue, more than a half-mile south of the main campus. Some WSNAC members felt the house was too far away fer the buyback program.

Several committee members commented on March 10 about the growing problems caused by families who buy houses near St. Thomas for their children and friends to live in while attending college. Those properties are usually homesteaded, which means they are not subject to the same kind of housing inspections that rental properties are. It is also harder to track those properties, which some WSNAC members describe as "de facto rental," through property records. University officials estimate that about 45 houses around the campus have been purchased by families for their student-child in recent years.

St. Thomas and WSNAC have encouraged neighbors to put deed restrictions on their own properties to block them from future rental use and offered informational packets on how to put the restrictions in place. However, many campus neighbors have balked at the notion.

Some WSNAC members would like to have seen the university create a community development corporation rather than try to buy problem properties house by house. St. Thomas has continued to seek houses to purchase and resell through the program, Hershey said, but some recent deals have fallen through due to prospective homeowners having trouble getting financing.




Monday, March 23, 2009

UST on HPC agenda

St. Paul Historic Preservation Commission public hearing regarding 2055 Summit--Sitzmann Hall- on Thursday, March 26.

University of St. Thomas is asking for a permit to construct an addition to roof and rear elevations. WSNAC has been active in the planning process with UST's building plans. See the WSNAC website for more details.

Monday, March 16, 2009

Summit Avenue Closed 3/22/2009

Sunday March 22, 2009:

11:30 AM to 2:30 PM: Summit Avenue closed between Cretin and Hamline
12:45 AM to 2:30 PM: Summit Avenue closed between Hamline and Victoria, and the streets surrounding William Mitchell College of Law.


There will be parking restrictions along the race route.

The Sporting life has obtained a parade permit for the City for the 36th annual St. Patrick's Day Human Race run/walk. For more details, check out the Human Race website or call 651-228-1986.

Sunday, February 22, 2009

UST expansion plans in the News

This Article in the Star Tribune reports on the UST's plans for a new student center and athletic facilities.

The article mentions, briefly, the participation of WSNAC and community members in the planning stages, but it leaves out the still unsettled controversy surrounding increased traffic and parking concerns.

Here's the article in its entirety:

St. Thomas trustees OK plans for athletic complex


By MARY LYNN SMITH, Star Tribune

February 20, 2009

As competition between colleges for new students gets tougher, the University of St.
Thomas will buff itself up with a new $52 million athletic and recreation complex and a $66
million student center on the university's main campus in St. Paul.

The project, another significant expansion of the school's presence in St. Paul, is the
largest in the university's history. Unlike previous construction efforts, it doesn't appear to
be inciting acrimony with neighborhood residents.

"This is a way of simply making sure we have the type of facilities that will help attract
students to the campus 10 and 15 years from now," said Mark Dienhart, the university's
executive vice president and chief operating officer.

In recent years, the university devoted a lot of time and money to building a downtown
Minneapolis campus and a law school, he said.

"While we were doing that, many of Minnesota's private colleges where we cross over with
applicants were building these kind of facilities," Dienhart said. "Our primary athletic facility
was built in 1939, and the student center was built for a population of 2,000."

St. Thomas' enrollment now totals nearly 11,000 with 7,460 students on the St. Paul
campus.

"These type of facilities, which are very important to students, just didn't match up to the
type of schools they were considering when they were looking at St. Thomas," Dienhart
said. "So we lost some students. We're trying to ensure the viability of the institution."
The university's board of trustees approved plans for the athletic and recreation complex
on Thursday, and construction will begin in late May. The 180,000-square-foot complex, to
be located east of the university's football stadium, is scheduled to be opened in fall 2010.
The board discussed the athletic complex in October but held off on approval because of
concerns about the weakened economy.

"Thanks to the support of generous contributors, we are able to move forward," said the
Rev. Dennis Dease, president of St. Thomas.

Construction of the proposed 240,000-square-foot student center, if approved next year by
the board of trustees, would begin in fall 2010 and be completed by February 2012.
The two projects and a 725-car parking ramp that opened earlier this week all will be
named for Lee and Penny Anderson, who made a $60 million gift to St. Thomas in 2007. It
is believed to be the largest single contribution by an individual or a couple to a college or
university in Minnesota and is part of St. Thomas' $500 million fundraising drive, which has raised $365 million to date.

The projects will be a bit of a boost to the local economy at a time when a downturn in
new construction has left many workers unemployed, Dienhart said.
The new facilities will significantly change the appearance of St. Thomas along both
Summit and Cretin avenues. But unlike the last major construction project, they likely will
rouse little if any neighborhood rancor.

A five-year feud over a campus expansion ended in 2004 after both sides drew up a 14-
page agreement that included establishing campus boundaries and the 12-member West
Summit Neighborhood Advisory Committee, a group of neighborhood and university
representatives who collaborate on issues concerning the campus and neighborhood.
"Our goal is peaceful coexistence," said Scott Banas, the advisory group's neighborhood
co-chair. "And we've been successful beyond my wildest dreams."

Before the parking ramp was built, the advisory group hashed out concerns, and the plans
were redrawn until the design was agreeable to both sides, Banas said.

The advisory group has been tweaking plans for the athletic complex for more than a
year, Banas said. "There's really been no major blow-up," he said. The "compromising
and conciliation" process will continue with plans for the student center, with the group
probably allaying neighborhood concerns about parking and pedestrian safety, he said.
The $15 million Anderson Parking Facility that opened earlier this month will allow the
university to close its parking lot at Summit and Cretin avenues. This will free up space for
the athletic complex, student center and a larger quadrangle. Some existing buildings also
will be replaced.

The new athletic complex will feature:
•A 2,000-seat basketball and volleyball arena.
•An aquatic center containing an eight-lane, 25-meter swimming pool and diving area.
•A new field house with a 200-meter track.
•A west wing with a fitness center, weight room and aerobic rooms on the first floor and
offices, classrooms and labs on the second and third floors.

Mary Lynn Smith • 612-673-4788
(c) Star Tribune 2009

Tuesday, February 17, 2009

Gail Fenske Lecture 7:00 PM tonight--don't miss!

From the University Club newsletter:

"Once the world’s tallest skyscraper, the Woolworth Building is noted for its striking but incongruous synthesis of Beaux-Arts architecture, fanciful Gothic ornamentation, and audacious steel-framed engineering. In the first history of this great urban landmark, Gail Fenske argues that its design serves as a compelling lens through which to view the distinctive urban culture of Progressive-era New York."